Concrete yardage calculator

Work out how much concrete a slab and its footings take. Enter the slab in feet and its thickness in inches, a continuous footing or a set of identical pads, and a waste allowance. The calculator shows cubic feet, cubic yards and the total with waste.

Concrete volume

Slab

Footing

Slab
500 ft³ = 18.52 yd³
Footing
133.33 ft³ = 4.94 yd³
Total neat volume
633.33 ft³ ÷ 27 = 23.46 yd³
With 10% waste
23.46 × 1.1 = 25.8 yd³
Rounded up to whole yards
26 yd³

Lengths are in feet; thickness, width and depth are in inches. Enter 0 in any slab or footing size to leave that part out. For pad footings, enter one pad's length and the number of pads. The waste percent is your own allowance.

Studying for NASCLA Commercial? Take the free 10-question check to see exactly which topics to fix first, then close the gaps with the Bid Bond course.

Or read a full free lesson first (no signup).

This is covered in Concrete, reinforcing, post-tensioning and precast of the Bid Bond course.

Studying with a coworker? Send them the free check.

The formula: feet, then divide by 27

Concrete is ordered by the cubic yard. A cubic yard is 3 ft × 3 ft × 3 ft, which is 27 cubic feet. The safe habit is to put every size in feet first, multiply, and divide by 27 last.

  • Slab cubic feet = length (ft) × width (ft) × thickness (in.) ÷ 12.
  • Footing cubic feet = number × length (ft) × width (in.) ÷ 12 × depth (in.) ÷ 12. For a continuous footing, the length is its run around the building. For square pads, it is one pad's side.
  • Cubic yards = cubic feet ÷ 27.
  • With waste = cubic yards × (1 + waste percent ÷ 100).

The waste allowance covers spillage, an uneven subgrade and the concrete left in the truck and pump. Pick your own figure, or use the one a question gives. The calculator rounds the total up to whole yards. Your supplier may sell in smaller steps, so ask.

Worked example 1: a slab with a perimeter footing

A slab is 50 ft by 30 ft and 4 in. thick. A footing runs 160 ft around it and is 12 in. wide and 10 in. deep. Waste is 10%. These are invented study numbers.

  1. Slab = 50 × 30 × 4 ÷ 12 = 1,500 × 0.3333 = 500 ft³, which is 500 ÷ 27 = 18.52 yd³.
  2. Footing = 160 × (12 ÷ 12) × (10 ÷ 12) = 160 × 1 × 0.8333 = 133.33 ft³, which is 4.94 yd³.
  3. Total = 500 + 133.33 = 633.33 ft³, and 633.33 ÷ 27 = 23.46 yd³.
  4. With 10% waste: 23.46 × 1.10 = 25.80 yd³, so order 26 yd³.

Check: 18.52 + 4.94 = 23.46, and 27 × 23.46 = 633.4, back to the cubic feet.

Worked example 2: six pad footings

Six pads are each 3 ft square and 12 in. deep, with 5% waste and no slab (enter 0 for the slab).

  1. Each pad = 3 × (36 ÷ 12) × (12 ÷ 12) = 3 × 3 × 1 = 9 ft³. Six pads = 54 ft³.
  2. 54 ÷ 27 = 2 yd³ exactly. With 5% waste, 2 × 1.05 = 2.1 yd³, which rounds up to 3 whole yards.

The second example shows why the rounding step is yours to judge: 2.1 yd³ is the quantity, and whether you order 2.25, 2.5 or 3 depends on what your supplier sells. These are original arithmetic examples, not exam questions.

Concrete yardage questions

Why divide by 27 and not by 9?

Nine converts square feet to square yards. Concrete is a volume, and a cubic yard holds 3 × 3 × 3 = 27 cubic feet.

Can I enter the slab thickness in feet?

The calculator takes inches and divides by 12 for you. A 4 in. slab is 0.3333 ft, and a 6 in. slab is 0.5 ft.

Where is this on the NASCLA exam?

Concrete is one of the twelve subject areas on the NASCLA outline, with 6 of the 115 scored questions. The Bid Bond course works this takeoff in its Concrete lesson.

See the NASCLA exam outline for all twelve subject areas and their question counts.

Multiply length by width by thickness in feet, divide by 27 for cubic yards and add your waste allowance, with every step shown. A study and estimating aid; the drawings and your supplier govern a real order.

Try one free question

Try one question

Question 1 of the free 10-question check on NASCLA Commercial. No signup. Then ask Seal, the AI study assistant, why the answer is right and the others are wrong.

Question 1 of 10 · free checkUntimed

Procurement and Contracting Requirements

A subcontractor on a bonded public project has not been paid for completed work. Which bond is meant to protect it?

Press A-D or 1-4 to choose an answer while this question is on screen.

Choose an answer to begin

Free NASCLA Commercial study plan

A week-by-week plan from today to your exam, weighted to the published exam outline. We show it here and email you a copy.

Ask Seal before you buy AI your AI study assistant

See what's on the NASCLA Commercial exam, test yourself with 5 quick questions, or find the plan that fits you.

Sources

From the blog

Practice NASCLA quantity questions

You just worked a concrete takeoff. The free 10-question NASCLA Commercial check scores you across the subject areas in minutes, needs no signup and explains every answer. The Bid Bond course drills the rest.

Take the free 10-question check

The NASCLA Commercial course

Available now · instant access

The NASCLA Commercial course

  • 12modules of lessonsEvery task on the outline
  • 4full-length timed exams115 questions in 330 minutes each
  • 472practice questionsEach one explained
  • 1week-by-week study planSet to your exam date

Turn a practice answer into a study step. In untimed practice, ask Seal AI about any question you answer, follow up, then see your weakest topics and what to drill next.

NASCLA Commercial course$199

Terms and refunds · Secure checkout by Stripe · Billed by Nori Software

See the course

Compare plans

Every answer comes with a full explanation.

By the Bid Bond editorial team. Report an error.

Add this calculator to your site

Copy this HTML with its attribution link. The frame scrolls to include the calculator and explanations; no external script is needed.