Bid bond vs performance bond vs payment bond

A bid bond, a performance bond and a payment bond are the three surety bonds of a construction contract. The bid bond promises that the low bidder will sign the contract and provide the other bonds. The performance bond promises that the work will be finished as the contract requires. The payment bond promises that subcontractors and suppliers will be paid.

Three bonds, three moments in a job

BondWhen it is givenWho it protectsWhat triggers a claim
Bid bondWith the bidThe ownerThe low bidder will not sign the contract or provide the required bonds
Performance bondAt contract signingThe ownerThe contractor defaults and does not complete the work
Payment bondAt contract signingSubcontractors and suppliersThey are not paid for labor or materials on the job

All three have the same three parties. The principal is the contractor. The obligee is the party the bond names, usually the owner. The surety stands behind the principal's promise. The bond amount is called the penal sum, and it caps what the surety owes under that bond.

Try one question

Question 1 of the free 10-question check on NASCLA Commercial. No signup. Then ask Seal, the AI study assistant, why the answer is right and the others are wrong.

Question 1 of 10 · free checkUntimed

Procurement and Contracting Requirements

A subcontractor on a bonded public project has not been paid for completed work. Which bond is meant to protect it?

Press A-D or 1-4 to choose an answer while this question is on screen.

Choose an answer to begin

A bond is not insurance for the contractor

Insurance spreads losses, and the insured does not repay the insurer. A surety expects no losses. Before it writes a bond, it has the contractor, and usually the owners of the contracting company personally, sign an indemnity agreement. If the surety pays a claim, it turns to the contractor to be repaid. That is why sureties look closely at a contractor's financial ratios, work in progress and experience before they bond a job.

Ask Seal before you buy AI your AI study assistant

See what's on the NASCLA Commercial exam, test yourself with 5 quick questions, or find the plan that fits you.

The NASCLA Commercial course

Available now · instant access

Learn all 12 subject areas and where to look in your books, then prove it on timed practice exams.

  • 12modules of lessonsEvery task on the outline
  • 4full-length timed exams115 questions in 330 minutes each
  • 472practice questionsEach one explained
  • 1week-by-week study planSet to your exam date

Turn a practice answer into a study step. In untimed practice, ask Seal AI about any question you answer, follow up, then see your weakest topics and what to drill next.

NASCLA Commercial course$199Get the course · $199

Instant access. Terms and refunds · Secure checkout by Stripe · Billed by Nori Software

Compare plans

Every answer comes with a full explanation.

Where each bond comes from

  • Bid bond. The invitation to bid says whether bid security is required and how much, often stated as a percentage of the bid. Some owners accept a certified or cashier's check instead. The what is a bid bond guide walks through a claim.
  • Performance and payment bonds. The contract or the law sets them. On federal construction, the Miller Act requires both above a dollar threshold that changes over time. Most states have similar laws for their own public work, often called Little Miller Acts, each with its own threshold and claim rules. Private owners require them by contract when they choose to.

Why public jobs lean on the payment bond

On private work, an unpaid subcontractor or supplier can usually file a mechanics' lien against the property. Public property generally cannot be liened, so the payment bond takes the place of lien rights. Notice and suit deadlines for a payment bond claim are set by the statute or the bond, and they differ by jurisdiction. Never answer one from memory. The lien waivers guide covers the private side.

A worked example with invented numbers

A contractor bids a public building at $1,850,000. The bid documents call for a bid bond of 5% of the bid and, if awarded, performance and payment bonds each at 100% of the contract.

  • Bid bond penal sum: 1,850,000 x 0.05 = $92,500. Check: 10% would be 185,000, and half of that is 92,500.
  • Performance bond penal sum: 1,850,000 x 1.00 = $1,850,000.
  • Payment bond penal sum: $1,850,000.

The surety charges one premium for the performance and payment bonds together. Using an invented rate of 1.1% of the contract: 1,850,000 x 0.011 = $20,350. Check: 1% is 18,500 and 0.1% is 1,850, and 18,500 + 1,850 = 20,350. Real rates vary by surety, contractor and job.

Now suppose the job is built and a drywall supplier is owed $38,000 that the contractor never paid. The supplier claims against the payment bond, not the performance bond, because the work was finished. If the surety pays the $38,000, it then collects that amount from the contractor under the indemnity agreement.

Common mix-ups

  • Calling the owner the principal. The contractor is the principal. The owner is the obligee.
  • Sending an unpaid sub to the performance bond. Unpaid labor and material claims go to the payment bond.
  • Treating the penal sum as the premium. The penal sum caps the surety's liability; the premium is its fee.

On the NASCLA exam

Bonds sit in Procurement and Contracting Requirements, the largest subject area at 31 of the 115 scored questions. Tab the bonds topic in the NASCLA Contractors Guide to Business, Law and Project Management. When a question asks who is protected, name the obligee first.

Practice it

Work the what is a bid bond claim example, then compare lien waivers on private jobs. The general liability vs builders risk vs workers comp guide covers the insurance side. On federal construction the Miller Act requires the performance and payment bonds; see the Miller Act and Little Miller Acts.

Take the free 10-question check

Start the free 10-question check. It is weighted to the twelve NASCLA subject areas, needs no signup and explains every answer, so you see which area to study first.

The NASCLA Commercial course has a lesson for each of the 12 subject areas that shows which listed reference to open and how to apply it, original practice questions with every answer worked, and four timed practice exams of 115 questions on a 330-minute clock. Your scores come back by subject area, so you know where the next study hour goes. See the course.

Not affiliated with or endorsed by NASCLA or PSI. NASCLA and PSI are named only to identify the exam and its test vendor.

Sources

Show the list

Facts come from the sources listed above. If something has changed, tell us and we will correct it within 2 business days.

Your next step

Ready to see where you stand on NASCLA Commercial?

Free, untimed and scored by domain. No signup.

Start the free 10-question check

NASCLA Commercial course. Lessons, timed practice exams and a plan around your exam date. Get NASCLA Commercial course · $199 See the plans or read the free sample lesson.Terms and refunds

Want a timed run? Try the free 25-question mini-mock. The first 5 need no email.

Prefer paper? Free printables

From the blog