A certificate of insurance (COI) is a one or two page summary, usually issued by the insurance agent or broker, showing that a company has certain policies with certain limits on the date it was issued. General contractors collect one from every sub before the sub starts work, and owners collect one from the general contractor. The most important thing to know about a certificate is what it is not: it is evidence of insurance, not the insurance. It does not add coverage, change the policy or make anyone an additional insured by itself.
What a certificate shows
- the named insured: the company the policies cover
- the insurers, policy numbers and policy dates
- each line of coverage and its limits, such as general liability, auto, workers' compensation and employer's liability, and umbrella or excess
- a description box that may mention the project, additional insured status or waiver of subrogation
- the certificate holder: the party that asked for the certificate
Certificate holder is not additional insured
The certificate holder is just the party that received the certificate. Being the holder gives no rights under the policy.
An additional insured is a party added to someone else's policy, usually a sub's commercial general liability (CGL) policy, so that it is covered for claims arising out of that sub's work. Additional insured status comes from an endorsement to the policy, either one naming the party or a blanket endorsement covering anyone the insured has agreed in a written contract to add. A line on the certificate saying "additional insured" is only a description of what the policy is said to contain. Ask for the endorsement itself when the contract requires it.
Endorsements come in two main kinds:
- Ongoing operations: covers claims while the sub's work is under way.
- Completed operations: covers claims that arise after the sub's work is finished, such as a collapse months after occupancy. Many contracts require this for a set period after completion.
Try one question
Question 1 of the free 10-question check on NASCLA Commercial. No signup. Then ask Seal, the AI study assistant, why the answer is right and the others are wrong.
Procurement and Contracting Requirements
A subcontractor on a bonded public project has not been paid for completed work. Which bond is meant to protect it?
Press A-D or 1-4 to choose an answer while this question is on screen.
Choose an answer to begin
Other terms that come with it
- Primary and noncontributory: the sub's policy pays first for the additional insured, without asking the general contractor's own policy to share.
- Waiver of subrogation: the insurer agrees not to sue the other party to recover what it paid. Usually also by endorsement.
- Notice of cancellation: many certificates say the insurer will try to notify the holder of cancellation, without promising to. Track expiry dates yourself.
How far these terms and the related indemnity clauses can go is limited by state law in some places, so read the contract and the law for the job. See general liability vs builder's risk vs workers' comp for what each line covers.
Ask Seal before you buy AI your AI study assistant
See what's on the NASCLA Commercial exam, test yourself with 5 quick questions, or find the plan that fits you.
The NASCLA Commercial course
Available now · instant accessLearn all 12 subject areas and where to look in your books, then prove it on timed practice exams.
- 12modules of lessonsEvery task on the outline
- 4full-length timed exams115 questions in 330 minutes each
- 472practice questionsEach one explained
- 1week-by-week study planSet to your exam date
Turn a practice answer into a study step. In untimed practice, ask Seal AI about any question you answer, follow up, then see your weakest topics and what to drill next.
Instant access. Terms and refunds · Secure checkout by Stripe · Billed by Nori Software
Every answer comes with a full explanation.
Checking a sub's certificate, with invented numbers
The subcontract requires CGL of $1,000,000 per occurrence and $2,000,000 aggregate, an umbrella of $5,000,000, and additional insured status for the general contractor on both ongoing and completed operations. The sub's certificate shows:
- CGL $1,000,000 per occurrence, $2,000,000 aggregate: meets it
- Umbrella $3,000,000: short by 5,000,000 - 3,000,000 = $2,000,000
- CGL policy ends 30 June; the sub's work runs to 15 August: expires mid-job
- "Additional insured" typed in the description box, no endorsement attached: ask for the endorsement
How the limits stack. Assume the umbrella sits over the CGL and follows its terms, and the claim is within both.
- A claim of $1,750,000: CGL pays 1,000,000, umbrella pays 1,750,000 - 1,000,000 = 750,000. Uncovered: $0.
- A claim of $4,600,000 with the sub's $3,000,000 umbrella: 1,000,000 + 3,000,000 = 4,000,000 paid. Uncovered: 4,600,000 - 4,000,000 = $600,000.
- The same claim with the required $5,000,000 umbrella: 1,000,000 + 5,000,000 = 6,000,000 available, so the whole $4,600,000 is covered.
Check: 4,000,000 + 600,000 = 4,600,000. The $600,000 gap would fall on the sub, and possibly the general contractor, which is why the shortfall gets fixed before the sub mobilizes. Real policies have exclusions and conditions that this simple stack leaves out.
A tracking routine
- Send each sub the insurance requirements with the bid package, not at contract signing.
- Check every certificate against the requirements, line by line, before the sub starts.
- Get the additional insured and waiver endorsements, not just the certificate.
- Log every expiry date and request renewals a month ahead.
- Hold payment, as the subcontract allows, when coverage lapses.
Common mix-ups
- Treating the certificate as coverage. It is evidence only. The policy and its endorsements decide.
- Holder versus additional insured. Holding a certificate adds no coverage.
- Forgetting completed operations. Many claims come after the work is done.
- Checking once. Policies expire during long jobs.
On the NASCLA exam
The bulletin lists subject areas, not topics. We place insurance and risk under Procurement and Contracting Requirements, 31 of the 115 scored questions. The NASCLA Contractors Guide to Business, Law and Project Management fits by its title, so tab its insurance and risk management topic.
Practice it
Read general liability vs builder's risk vs workers' comp for the policies behind the certificate, and notice to proceed and contract time for why owners want certificates before work starts.
Take the free 10-question check
Start the free 10-question check. It is weighted to the twelve NASCLA subject areas, needs no signup and explains every answer, so you see which area to study first.
The NASCLA Commercial course has a lesson for each of the 12 subject areas that shows which listed reference to open and how to apply it, original practice questions with every answer worked, and four timed practice exams of 115 questions on a 330-minute clock. Your scores come back by subject area, so you know where the next study hour goes. See the course.
Not affiliated with or endorsed by NASCLA or PSI. NASCLA and PSI are named only to identify the exam and its test vendor.
Sources
Show the list
- PSI Candidate Information Bulletin 1458, content outline and reference list, updated 7 Jul 2026. Retrieved 5 Nov 2026.
- NASCLA Commercial Exam, NASCLA. Retrieved 5 Nov 2026.
- All examples use invented numbers and a simplified stack. Real coverage depends on each policy's terms and state law.
Facts come from the sources listed above. If something has changed, tell us and we will correct it within 2 business days.
Your next step
Ready to see where you stand on NASCLA Commercial?
Free, untimed and scored by domain. No signup.
Start the free 10-question checkNASCLA Commercial course. Lessons, timed practice exams and a plan around your exam date. Get NASCLA Commercial course · $199 See the plans or read the free sample lesson.Terms and refunds
Want a timed run? Try the free 25-question mini-mock. The first 5 need no email.
Prefer paper? Free printables
- Print a class quiz (free PDF). 10 practice questions with an answer key on page 2.
- Print the flashcards as cut-out cards (free PDF). The free flashcard sample, ready to cut and carry.
From the blog
- From contract award to the first pay application
- Subcontractor buyout without bid shopping
- Bidding public work for the first time