Over and under billing calculator

Check one job on a work-in-progress schedule. Enter the contract value, the estimated total cost, the cost to date and the amount billed to date. The calculator gives percent complete by the cost-to-cost method, the revenue earned so far, and whether the job is overbilled or underbilled and by how much.

Contract, cost and billing

Percent complete = cost to date ÷ estimated total cost
$300,000.00 ÷ $800,000.00 = 37.5%
Earned revenue = percent complete × contract value
37.5% × $1,000,000.00 = $375,000.00
Check: cost to date × (contract ÷ estimated cost)
$300,000.00 × 1.25 = $375,000.00
Billed to date − earned revenue
$420,000.00 − $375,000.00 = $45,000.00
Result
Overbilled by $45,000.00, a liability (billings in excess of costs and estimated earnings)
Estimated gross profit on the job
$1,000,000.00 − $800,000.00 = $200,000.00
Gross profit earned to date
$375,000.00 − $300,000.00 = $75,000.00
Estimated cost to complete
$500,000.00
Share of the contract billed
42%

Use the contract value with approved change orders, and an estimated total cost that is current: cost to date plus a fresh estimate of the cost to complete. Cost to date is the cost of work in place on the job, not what has been paid. A study and planning aid; your accountant decides how jobs are reported.

Studying for NASCLA Commercial? Take the free 10-question check to see exactly which topics to fix first, then close the gaps with the Bid Bond course.

Or read a full free lesson first (no signup).

This is covered in Procurement, contracting and running the business of the Bid Bond course.

Studying with a coworker? Send them the free check.

The formula: cost-to-cost percent complete

On jobs reported by percentage of completion, revenue is earned as the work progresses. The cost-to-cost method measures progress by the share of the estimated total cost spent so far. Billing ahead of that earned revenue is an overbilling, a liability, because the company owes the work. Billing behind it is an underbilling, an asset.

  • Percent complete = cost to date ÷ estimated total cost.
  • Earned revenue = percent complete × contract value.
  • Billed to date − earned revenue is an overbilling when positive and an underbilling when negative.
  • Gross profit to date = earned revenue − cost to date.

Worked example 1: an overbilled job

A $1,000,000 contract has an estimated total cost of $800,000. Cost to date is $300,000 and $420,000 has been billed. These are invented study numbers and the calculator's starting example.

  1. Percent complete = 300,000 ÷ 800,000 = 37.5%.
  2. Earned revenue = 0.375 × 1,000,000 = $375,000.
  3. Billed − earned = 420,000 − 375,000 = $45,000 overbilled.
  4. Gross profit to date = 375,000 − 300,000 = $75,000.

Check: each dollar of cost earns 1,000,000 ÷ 800,000 = 1.25 dollars of revenue, and 300,000 × 1.25 = 375,000. The job's estimated gross profit is 1,000,000 − 800,000 = 200,000, and 37.5% of 200,000 = 75,000, the same gross profit to date.

Worked example 2: an underbilled job

A $2,400,000 contract has an estimated total cost of $2,000,000. Cost to date is $1,300,000 and $1,450,000 has been billed.

  1. Percent complete = 1,300,000 ÷ 2,000,000 = 65%.
  2. Earned revenue = 0.65 × 2,400,000 = $1,560,000.
  3. Billed − earned = 1,450,000 − 1,560,000 = −110,000, so $110,000 underbilled.
  4. Gross profit to date = 1,560,000 − 1,300,000 = $260,000.

Check: 2,400,000 ÷ 2,000,000 = 1.2, and 1,300,000 × 1.2 = 1,560,000. The estimated gross profit is 400,000, and 65% of 400,000 = 260,000. An underbilling this size is worth a look: it can be unbilled change order work, or a cost overrun that the estimated total cost has not caught up with yet. These are original arithmetic examples, not exam questions. The job costing and overhead guide covers the job cost report behind these numbers, and bonding capacity explains why sureties read the WIP schedule.

Over and under billing questions

How do you calculate over and under billing?

Find percent complete as cost to date ÷ estimated total cost, multiply by the contract value for earned revenue, and subtract that from billed to date. A $1,000,000 contract with $800,000 of estimated cost, $300,000 of cost to date and $420,000 billed is 37.5% complete, has earned $375,000 and is $45,000 overbilled.

Is overbilling an asset or a liability?

Overbilling (billings in excess of costs and estimated earnings) is a liability, because the company has been paid for work it still owes. Underbilling (costs and estimated earnings in excess of billings) is an asset, because the company has earned revenue it has not billed yet.

Why does underbilling worry sureties and banks?

It can mean unbilled change order work, or a cost overrun the estimated total cost has not caught up with. In the second worked example a job 65% complete has earned $1,560,000 but billed $1,450,000, so it is $110,000 underbilled.

Where is this on the NASCLA exam?

The Bid Bond course teaches percentage of completion and over and under billing in its Procurement and Contracting Requirements lesson. That is the largest of the twelve subject areas on the NASCLA outline, with 31 of the 115 scored questions.

See the NASCLA exam outline for all twelve subject areas and their question counts.

Divide cost to date by the estimated total cost for percent complete, apply it to the contract value for earned revenue, and compare billings with it, with every step shown. A study and planning aid; your accountant decides how jobs are reported.

Try one free question

Try one question

Question 1 of the free 10-question check on NASCLA Commercial. No signup. Then ask Seal, the AI study assistant, why the answer is right and the others are wrong.

Question 1 of 10 · free checkUntimed

Procurement and Contracting Requirements

A subcontractor on a bonded public project has not been paid for completed work. Which bond is meant to protect it?

Press A-D or 1-4 to choose an answer while this question is on screen.

Choose an answer to begin

Free NASCLA Commercial study plan

A week-by-week plan from today to your exam, weighted to the published exam outline. We show it here and email you a copy.

Ask Seal before you buy AI your AI study assistant

See what's on the NASCLA Commercial exam, test yourself with 5 quick questions, or find the plan that fits you.

Sources

From the blog

Practice NASCLA business questions

You just worked a job on a WIP schedule. The free 10-question NASCLA Commercial check scores you across the subject areas in minutes, needs no signup and explains every answer. The Bid Bond course drills the rest.

Take the free 10-question check

The NASCLA Commercial course

Available now · instant access

The NASCLA Commercial course

  • 12modules of lessonsEvery task on the outline
  • 4full-length timed exams115 questions in 330 minutes each
  • 472practice questionsEach one explained
  • 1week-by-week study planSet to your exam date

Turn a practice answer into a study step. In untimed practice, ask Seal AI about any question you answer, follow up, then see your weakest topics and what to drill next.

NASCLA Commercial course$199

Terms and refunds · Secure checkout by Stripe · Billed by Nori Software

See the course

Compare plans

Every answer comes with a full explanation.

By the Bid Bond editorial team. Report an error.

Add this calculator to your site

Copy this HTML with its attribution link. The frame scrolls to include the calculator and explanations; no external script is needed.