NASCLA Procurement and Contracting guide
Procurement and Contracting Requirements is the largest subject area on the NASCLA Commercial General Building exam: 31 of the 115 scored questions, about 27%. It covers how work is bought and sold and how a contracting business is run. Much of it is arithmetic you can do faster than any lookup, which makes it the best place to bank points.
Check anything you rely on against your own licensed code book and the edition your AHJ enforces.
What the bulletin says, and what it leaves out
PSI's Candidate Information Bulletin (updated 7 Jul 2026) gives the area name and its count of 31, with no topic list. The topics below are our reading of the area name and the reference list. They are not a list NASCLA publishes.
Topics to cover
- Bidding and estimating. Bid packages, addenda, responsive bids and responsible bidders, kinds of estimate, quantity takeoff, labor productivity and labor burden, unit-price bids.
- Markup and margin. The most common arithmetic trap in the area.
- Bonds and insurance. The three parties to a surety bond; bid, performance and payment bonds; general liability, workers' compensation, builder's risk; additional insured, waiver of subrogation and indemnity clauses.
- Contracts and delivery. Lump sum, unit price, cost plus a fee, and cost plus a fee with a maximum price cap (GMP); design-bid-build, design-build and construction management.
- Changes and payment. Change orders and directives, written notice, payment applications, retainage, liens and lien waivers.
- The business. Business forms, financial statements, break-even, ratios, depreciation, payroll, federal employment rules and tax forms.
Try one question
Question 1 of the free 10-question check on NASCLA Commercial. No signup. Then ask Seal, the AI study assistant, why the answer is right and the others are wrong.
Procurement and Contracting Requirements
A subcontractor on a bonded public project has not been paid for completed work. Which bond is meant to protect it?
Press A-D or 1-4 to choose an answer while this question is on screen.
Choose an answer to begin
Books to open first
Our suggestion from the titles. NASCLA publishes no mapping.
- NASCLA Contractors Guide to Business, Law and Project Management: the core book for this area.
- Construction Project Management: delivery methods and contract types.
- Construction Jobsite Management: changes and payment paperwork in the field.
Ask Seal before you buy AI your AI study assistant
See what's on the NASCLA Commercial exam, test yourself with 5 quick questions, or find the plan that fits you.
The NASCLA Commercial course
Available now · instant accessLearn all 12 subject areas and where to look in your books, then prove it on timed practice exams.
- 12modules of lessonsEvery task on the outline
- 4full-length timed exams115 questions in 330 minutes each
- 472practice questionsEach one explained
- 1week-by-week study planSet to your exam date
Turn a practice answer into a study step. In untimed practice, ask Seal AI about any question you answer, follow up, then see your weakest topics and what to drill next.
Instant access. Terms and refunds · Secure checkout by Stripe · Billed by Nori Software
Every answer comes with a full explanation.
Worked examples
All numbers are invented. Each is worked two ways.
Markup versus margin. Direct cost is $250,000.
- A 12% markup gives 250,000 x 1.12 = $280,000. The profit is $30,000, so the margin is 30,000 / 280,000 = 10.71%. Check: 0.12 / 1.12 = 0.1071.
- A 12% margin needs 250,000 / 0.88 = $284,090.91. Check: 284,090.91 x 0.88 = 250,000.00.
Bidding a 12% markup when you needed a 12% margin leaves 284,090.91 minus 280,000 = $4,090.91 on the table.
Retainage on a pay application. Work completed to date is $540,000, retainage is 5%, and previous payments total $400,000. Retainage held is 540,000 x 0.05 = $27,000. Earned less retainage is 540,000 minus 27,000 = $513,000. This payment is 513,000 minus 400,000 = $113,000. Check: 540,000 x 0.95 = 513,000, and 400,000 + 113,000 = 513,000.
Federal overtime. A nonexempt employee earns $32 an hour and works 44 hours in one workweek. Straight time is 40 x 32 = $1,280, and overtime is 4 x 48 = $192, so gross pay is $1,472. Check: 44 x 32 = 1,408, plus a half-time premium of 4 x 16 = 64, gives 1,472.
Break-even. Annual overhead is $270,000 and the gross profit rate is 18%. Break-even revenue is 270,000 / 0.18 = $1,500,000. Check: 18% of 1,500,000 is 270,000.
State rules versus federal rules
This is a multi-state exam, so watch which kind of rule a question is about.
- Set by each state: lien notice and filing deadlines, who may file, licensing rules, and bond thresholds on state and local public work. Never answer one of these from memory as if it applied everywhere.
- Federal and the same everywhere: overtime at 1.5 times the regular rate for hours past 40 in a workweek under the FLSA, Form I-9 for every new hire, Form W-4 for withholding, Form 941 each quarter, and the employer matching the employee's Social Security and Medicare share. The Miller Act covers bonds on federal work.
Avoid memorizing dollar thresholds and wage bases that change each year.
Common mix-ups
- A bond is not insurance for the contractor. It protects the owner or the unpaid parties, and the contractor repays the surety.
- Markup is on cost; margin is on price. Write the formula before the numbers.
- Retainage base. Read whether the question retains on stored materials as well as completed work.
- Salvage value. Subtract it in straight-line depreciation, not before applying a declining-balance rate.
How to practice
Do arithmetic sets until each formula is automatic, then spend book time on bonds, insurance and contract terms. Tab the business and law topics in the Contractors Guide first, because this is the area with the most questions. The NASCLA study guide gives it two weeks, and the exam outline shows how it compares with the other areas. The second-largest area is General Requirements.
Practice it
Price a bid with the free markup and margin calculator and check a pay application with the retainage calculator. The break-even calculator finds the sales volume that covers overhead. Term guides for this area include bid shopping and bid peddling, bonding capacity, certificates of insurance, Davis-Bacon prevailing wage and the Miller Act.
Take the free 10-question check and see your score by subject area in minutes. It needs no signup and explains every answer.
The NASCLA Commercial course has a lesson for each of the 12 subject areas that shows which listed reference to open and how to apply it, original practice questions with every answer worked, and four timed practice exams of 115 questions on a 330-minute clock. Your scores come back by subject area, so you know where the next study hour goes. See the course.
Not affiliated with or endorsed by NASCLA or PSI. NASCLA and PSI are named only to identify the exam and its test vendor.
Sources
Show the list
- PSI Candidate Information Bulletin 1458, content outline and reference list, updated 7 Jul 2026. Retrieved 5 Nov 2026.
- Overtime Pay, U.S. Department of Labor, Wage and Hour Division.
Facts come from the sources listed above. If something has changed, tell us and we will correct it within 2 business days.
Your next step
Ready to see where you stand on NASCLA Commercial?
Free, untimed and scored by domain. No signup.
Start the free 10-question checkNASCLA Commercial course. Lessons, timed practice exams and a plan around your exam date. Get NASCLA Commercial course · $199 See the plans or read the free sample lesson.Terms and refunds
Want a timed run? Try the free 25-question mini-mock. The first 5 need no email.
Free tools for this topic
Prefer paper? Free printables
- Print a class quiz (free PDF). 10 practice questions with an answer key on page 2.
- Print the flashcards as cut-out cards (free PDF). The free flashcard sample, ready to cut and carry.
From the blog
- Reading a bid package like an examiner
- The 31 NASCLA procurement questions: where the points are
- A 12-week NASCLA study plan for working contractors