Step flashing vs counterflashing: what it means on an inspection
Step flashing is a series of small bent metal pieces, one per shingle course, that seal where a sloping roof meets a wall that rises above it. Counterflashing is a separate cap piece fixed to the wall or chimney that laps over the top edge of the flashing below. Step flashing is woven in, and counterflashing is placed over.
Use this diagram
How to tell them from each other, and check them
- Find where the roof meets a wall. Along a sidewall, where the roof slopes up to a wall that rises above it, step flashing goes in. Each piece is bent in an L, laid over a shingle course, and the next course covers its lower portion.
- Check the lap. Each step piece goes under the siding or wall covering above and over the shingle below. Water that gets past a shingle lands on the metal and runs down to the next course.
- Find the chimney or masonry wall. Here the base flashing sits at the roof and the counterflashing is a second piece set into the masonry or fixed to the wall above, folding down over the base flashing.
- Check the order. Counterflashing must lap over the base flashing, never under it, so water falling down the wall lands on the cap and drops onto the base.
- Check the attachment. The cap is fixed to the wall, usually in a joint or slot, and the base is fixed to the roof. The two move independently, which is why they are separate pieces.
Try one question
Question 1 of the free 10-question check on ICC B1. No signup. Then ask Plumb, the AI study assistant, why the answer is right and the others are wrong.
Public Safety and Special Construction
In a new bedroom, the only emergency escape window has a keyed sash lock, with the key hanging on a hook beside the window. What should the inspector do?
Press A-D or 1-4 to choose an answer while this question is on screen.
Choose an answer to begin
Common mix-ups
- Step flashing versus continuous flashing. With shingles, a single long strip along a sidewall does not let each course lap properly. The step pieces exist for that reason.
- Counterflashing versus cap flashing. Many people use the two terms for the same piece. The idea is the same: a cover piece that laps over a base piece.
- Counterflashing versus a kick-out piece. A diverter at the bottom of a sidewall, where a roof ends against a wall, sends water into the gutter. It is a different part.
- Base flashing versus step flashing. At a chimney, the front and back often use different pieces than the sides, where step flashing is used.
Ask Plumb before you buy AI your AI study assistant
See what's on the ICC B1 exam, test yourself with 5 quick questions, or find the plan that fits you.
The ICC B1 course
Available now · instant accessLearn how the IRC is laid out, drill finding sections fast, then practice. Written for the 2024 IRC.
- 7modules of lessonsEvery task on the outline
- 4full-length timed exams60 questions in 120 minutes each
- 426practice questionsEach one explained
- 4worked calculationsStep by step
- 8timed code lookups a setFind it fast in IRC, with your median time
- 1week-by-week study planSet to your exam date
Turn a practice answer into a study step. In untimed practice, ask Plumb AI about any question you answer, follow up, then see your weakest topics and what to drill next.
Instant access. Terms and refunds · Secure checkout by Stripe · Billed by Nori Software
Every answer comes with a full explanation.
Roof flashing on the B1
Roof flashing is part of the roof assemblies chapter, Chapter 9 of the IRC, and wall flashing is in Chapter 7. The roof and ceiling area is 14% of the B1 and wall coverings are in the 27% wall area. Expect a roof-to-wall or chimney scenario with a lapping question. Look up the roof flashing sections by name, and confirm their numbers in your edition before you tab them.
Practice it
Pair this with flashing, which covers where flashing goes on walls and openings, and roof pitch, which relates steepness to the roof coverings that need it. The IRC chapters guide shows where Chapters 7 and 9 sit, and the IRC terms glossary lists every term page.
Know your roof flashing? Check the rest of the B1
Take the free 10-question check. It is weighted to the seven B1 areas, scored by area and needs no signup, so you see which area costs you the most points. The Rafter Tie course adds timed practice exams, a lesson for each outline area and a study plan built from your exam date.
Sources
Show the list
- B1 Residential Building Inspector Content Outline, International Code Council.
- 2021 IRC contents and 2024 IRC contents, International Code Council. Chapters are named, not quoted; open your own copy for the text.
Facts come from the sources listed above. If something has changed, tell us and we will correct it within 2 business days.
Your next step
Ready to see where you stand on ICC B1?
Free, untimed and scored by domain. No signup.
Start the free 10-question checkB1 course with IRC navigation drills. Lessons, timed practice exams and a plan around your exam date. Get B1 course with IRC navigation drills · $99 See the plans or read the free sample lesson.Terms and refunds
Want a timed run? Try the free 25-question mini-mock. The first 5 need no email.
Prefer paper? Free printables
- Print the study checklist (free PDF). Topics to cover, on one printable page. No email.
- Print a class quiz (free PDF). 5 practice questions with an answer key on page 2.
- Print the flashcards as cut-out cards (free PDF). The free flashcard sample, ready to cut and carry.
From the blog
- ICC B1 exterior coverings and weather barriers
- IRC wall bracing for inspectors: lines and panels
- ICC B1 egress, stairs and guards: what to measure